Time and Work: Z number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. What is the original number of men?

Step-by-step solution. Time and Work for UPSC CDS/OTA.

Topic
Time and Work
Subject
Mathematics
Difficulty
Medium
Solve Time
45-60 sec

Solved UPSC CDS/OTA Question

A solved UPSC CDS/OTA PYQ - decoded step-by-step.

Solve it the standard way once - then learn the shortcut.

Q · Time and WorkMedium · 45s

Z number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. What is the original number of men?

TopicTime and Work
Question Typemultiple choice
DifficultyMedium
Marking+1 / −0.25
Test Duration30 min

Step-by-Step Solution

The complete worked solution.

Every step explained - no skipped algebra.

Solution illustration 1
Final Answer: Option A - 10