Time and Work · UPSC CDS/OTA · Question 49 of 60

Time and Work – Question 49

Step-by-step solution. Time and Work for UPSC CDS/OTA.

Topic
Time and Work
Subject
Mathematics
Difficulty
Medium
Solve Time
45–60 sec

Solved UPSC CDS/OTA Question

A solved UPSC CDS/OTA PYQ — decoded step-by-step.

Solve it the standard way once — then learn the shortcut.

Q · Time and WorkMedium · 45s

The Bubna dam has four inlets. Through the first three inlets, the dam can be filled in 12 minutes, through the second, the third and the fourth inlets, it can be filled in 15 minutes; and through the first and the fourth inlet, in 20 minutes. How much time will it take all the four inlets to fill up the dam?

TopicTime and Work
Question Typemultiple choice
DifficultyMedium
Marking+1 / −0.25
Test Duration30 min

Step-by-Step Solution

The complete worked solution.

Every step explained — no skipped algebra.

Solution illustration 1Solution illustration 2
Final Answer: Option B — 10 min