An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds only 2.5 km of the road has been completed(d) Find the (approx.) number of extra men he must employ to finish the work in time.

TopicTime and Work
Question Typemultiple choice
DifficultyMedium
Marking+1 / −0.25
Test Duration30 min

Step-by-Step Solution

The complete worked solution.

Every step explained — no skipped algebra.

Solution illustration 1
Final Answer: Option B — 45