Independence Day Sale is liveGet up to 75% OFFGrab the offer
Time and Work · UPSC CDS/OTA · Question 30 of 105

Time and Work: An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds only 2.5 km of the road has been completed(d) Find the (approx.) number of extra men he must employ to finish the work in time.

Step-by-step solution. Time and Work for UPSC CDS/OTA.

Topic
Time and Work
Subject
Mathematics
Difficulty
Medium
Solve Time
45-60 sec

Solved UPSC CDS/OTA Question

A solved UPSC CDS/OTA PYQ - decoded step-by-step.

Solve it the standard way once - then learn the shortcut.

Q · Time and WorkMedium · 45s

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds only 2.5 km of the road has been completed(d) Find the (approx.) number of extra men he must employ to finish the work in time.

TopicTime and Work
Question Typemultiple choice
DifficultyMedium
Marking+1 / −0.25
Test Duration30 min

Step-by-Step Solution

The complete worked solution.

Every step explained - no skipped algebra.

Solution illustration 1
Final Answer: Option B - 45
Solve Question✦ Build Plan
An engineer undertakes a project to build a road 15 km… - Time and Work (Mathematics) Solved Question