Q · Time and WorkMedium · 45s

Ajit can do as much work in 2 days as Baljit can do in 3 days and Baljit can do as much in 4 days as Diljit in 5 days. A piece of work takes 20 days if all work together. How long would Baljit take to do all the work by himself?

TopicTime and Work
Question Typemultiple choice
DifficultyMedium
Marking+1 / −0.25
Test Duration30 min

Step-by-Step Solution

The complete worked solution.

Every step explained — no skipped algebra.

Solution illustration 1
Final Answer: Option B — 44 days