A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in?

TopicTime and Work
Question Typemultiple choice
DifficultyMedium
Marking+1 / −0.25
Test Duration30 min

Step-by-Step Solution

The complete worked solution.

Every step explained — no skipped algebra.

Solution illustration 1
Final Answer: Option B — 5 days